Winter-2015
Get solved
assignments at nominal price of Rs.125 each.
Mail us at: subjects4u@gmail.com or contact at
09882243490
Master of
Business Administration - MBA Semester 3
PM0010-Introduction
to Project Management
(Book ID:
B1936)
Assignment
(60 Marks)
Note: Answers
for 10 marks questions should be approximately of 400 words. Each question is
followed by evaluation scheme. Each Question carries 10 marks 6 X 10=60.
Q1. a. Describe the characteristics
of a project
b. Explain the triple constraints in
project management.
Answer. a. Characteristics of a
project
b. Triple Constraints:
All projects are carried out under certain constraints –
traditionally, they are cost, time and scope. These three important factors
(commonly called "the triple constraint") are often represented as a
triangle.
Q2. Write short notes on:
Ø Project development
Ø Project organisation
Ø Factors affecting collection of market-related information
Ø Term loans as a means of financing projects.
Answer. Project
Development is the process that takes a transportation improvement from concept
through construction. There are several goals for this process:
Ø To ensure context
sensitivity though an open, consensus-building dialog among project proponents,
reviewers, the public, and other parties.
Ø To foster thinking
beyond the roadway pavement to achieve the optimum accommodation for all modes.
Ø To encourage early
planning, public outreach, and evaluation so that project needs, goals and
objectives, issues, and impacts can be identified before significant resources
are expended.
Q3. Explain the L-M
approach of SCBA.
Answer. L-M
Approach:
I.M.D
Little & J.A.Mirlees have developed this approach for analysis of Social
Cost-Benefit in Manual of Industrial Project Analysis in Developing Countries and
Project Appraisal & Planning for Developing Countries.
The L.M.
Approach to Social Cost has considerable similarity with the UNIDO approach. In
the first place, both the approach use shadow (accounting) prices for foreign
exchange savings and unskilled labor in particular. Similarly, both consider
factor of equity. And finally both the
Q4. Discuss the
financing of a power project.
Answer. Project
financing is often
referred to as “non-recourse” or “limited recourse”. Nonrecourse lending is
however inconceivable as it is unlikely that the lending institutions will
enter into financing arrangements without some sort of recourse or remedy to
the assets of the borrower in the event of a breach. The term is therefore
rarely used. The more apt term would be the limited recourse financing, where
lenders’ remedies are restricted to the secured assets of the project company
only.
Project
Finance techniques have been stated to be the best option for the financing of
power projects. Some of the possible reasons that explain this are considered
below:
1. Project
Finance which is sometimes called ‘off-balance sheet financing does exactly
what its alternative name implies: it takes the risks off the balance sheet of
a company, so that a failure of
Q5. Explain the types
of procurement contracts.
Answer. A contract is
nothing but a legally binding agreement between two or more parties. Usually
one party is known as a buyer and another as a seller. The contract is the key
between the buyer and seller relationship. It determines the way they will deal
with each other.
Procurement
contracts can be broadly divided into three categories:
Ø Fixed Price Contract
Ø Cost Reimbursable Contract, and
Ø Time and Materials
Fixed Price
Contract
A Fixed
Price Contract is also known as a lump-sum contract. This type of contract is
used when there is no uncertainty in the scope of work. Once the contract is
signed, the seller is legally bound to complete the task within the agreed
amount of money or time. Since the seller has to complete the task within a
fixed amount, he bears the risks.
Q6. What is the
purpose of project evaluation? Which the four dimensions of the project explain
the purpose of project evaluation?
Answer. Purpose:
1. Analyse
the process of implementation, focusing on participation of the community
2. Analyse
the impact or changes that have occurred within beneficiary households and the
community
3. Identify
problems and constraints that have been encountered
Winter-2015
Get solved
assignments at nominal price of Rs.125 each.
Mail us at: subjects4u@gmail.com or contact at
09882243490
No comments:
Post a Comment